Construction Updates

East Side of Mille Lacs Lake (2027 Project)

Status: Planning & Sign-Up Phase

This major broadband expansion project is scheduled for construction in 2027 and will bring MLEC Fiber service to approximately 1,500 homes, businesses, resorts, campgrounds, and RV parks along the east side of Mille Lacs Lake.

Current Progress

  • Project planning and engineering activities are underway.
  • Outreach mailings have been sent to residents and businesses in the project area.
  • Early sign-ups are being accepted.
  • Construction is expected to begin in 2027.

 

South Tame Fish

Status:  Service Available / Construction

Current Progress

  • The north portion of the South Tame Fish project is complete, and customer installations are now underway.

  • On the south portion, construction is nearing completion. Splicing and testing will be the next steps as we move closer to connecting customers.